Section: Grenfell Tower

Leaked Grenfell dossier reveals how disastrous refurbishment turned tower into a 'tinderbox'

Posted 17.04.18
Evening Standard: Article link

A report prepared as part of the police investigation into the Grenfell Tower fire has uncovered calamitous deficiencies in the installation of the windows, cavity barriers and cladding system, and their failure to meet building regulations.

The 210-page interim document, by fire investigation experts BRE Global, is set to dramatically assist the Metropolitan police in their wide-ranging investigation.

It was leaked exclusively to the Standard and recounts in forensic detail how the original concrete building was turned from a safe structure into a tinderbox by the refurbishment between 2014 and 2016.

It not only finds the cladding material and insulation was combustible, but also exposes hitherto unknown areas of incompetence relating to the design and installation of the windows and cavity barriers.

KeyFacts


KeyFacts provides an easy way to keep up-to-date with issues affecting the UK's social and affordable housing sectors


Selected news and views is reported in summary format, with links to source articles for further reading if required


Watch out for Quick Links - to avoid too much content, we sometimes list headlines only with links to source articles


Summary articles and Quick Links are posted to recognisable sub-sections for easy access - now and at a future date


KeyFacts is an essential free resource for anyone with a busy daily schedule



Enter your email address to receive our e-newsletters advising on updates to KeyFacts

We will not share your email address with others or use it for any other purpose

Reporting on April 2018

Site Sections

Bookmark and Share

Current Issue